10-Year Capital Improvement Plan
APRIL 2010 by D. STUMPH, DIRECTOR of OPERATIONS
ANNUAL ASSESSMENTS ARE COMPLETED AND THE CAPITAL
PROJECTS SCHEDULE IS REVISED ACCORDINGLY 
MIDDLE SCHOOL NEW CONSTRUCTION - OPEN JAN. 2004
   
2009-2019 BAY VILLAGE CITY SCHOOLS 10 YEAR PLAN SUBJECT  TO CHANGE
SCHOOL ITEM

YEAR

ESTIMATE

ACTUAL

 

STATUS

HIGH SCHOOL SHOWER INSTALL PARTITIONS GIRLS LOCKER ROOM 2009 $2,000 $1,852 COMPLETE
HIGH SCHOOL CEMENT REPAIR / PARKING LOT REPAIR 2009 $20,000 $61,575 UNSUITABLE SOIL COMPLETE
HIGH SCHOOL added PARKING LOT STRIPING 2009 $3,760 $3,760 COMPLETE
HIGH SCHOOL ROOF REPAIR SEAM REPAIR AUDITORIUM + SOUTH CLASS 2009 $6,000 $16,623 COMPLETE
HIGH SCHOOL WINDOW RE-TUCK 2009 $1,000 In-Progress 
HIGH SCHOOL WINDOWS 18 ROOMS - SMALL WINDOWS 204-214 101-107 DELAYED 2009 $16,352 $0 DELAYED
HIGH SCHOOL CARPET MAIN,PRINCIPAL, AP 2009 $5,000 DELAYED
HIGH SCHOOL RE-WIRE AUDITORIUM SOUND SYSTEM 2009 $0 In-progress
HIGH SCHOOL CARPET ANNUAL 2009 $4,000 COMPLETE
HIGH SCHOOL KITCHEN COUNTERS, CEILING FANS, ETC 2009 $3,000 $1,000 COMPLETE
$61,112
MIDDLE SCHOOL SIDEWALK REPLACEMENT BACK DELAYED 2009 $5,000 $0   COMPLETE
WESTERLY ROOF B REPLACEMENT 16,000 SQ FT 2009 $80,000 $71,625 COMPLETE
WESTERLY added Seam repair, fascia change order 2009 $12,535 $12,535 COMPLETE
WESTERLY CLASSROOM DROP CEILINGS (8) Classrooms 2009 $24,000 $19,920 COMPLETE
WESTERLY CLASSROOM LIGHTING REPLACEMENT (8) Classrooms 2009 $8,000
$124,535

2009 TOTALS

 
NORMANDY BOILER STEP REPAIR 2009 $1,000 $200   COMPLETE
NORMANDY DOOR CLOSURE REPLACE FRONT 2009 $3,000 $2,500   COMPLETE
NORMANDY PAVE HANDICAP RAMPS  DELAYED 2009 $1,000 $0   DELAYED
NORMANDY LIBRARY ROOF SEAM WORK 2009 $2,500 $1,986   COMPLETE
NORMANDY CARPET  DELAYED 2009 $4,000 $0   DELAYED
NORMANDY CLASSROOM SINK / DRINKING FOUNTAIN REPAIR 2009 $10,000 $2,500   COMPLETE
$21,500 $7,186    
 
 
GLENVIEW ROOF A REPLACE  15,000 SQ FT $6 Sq Ft Tear-off Needed 2009 $90,000 $68,941 COMPLETE
GLENVIEW WINDOW ROOM 109 2009 $7,850 $7,450 COMPLETE
GLENVIEW CARPET MAIN OFFICE/DIRECTOR - GLENVIEW BUDGET 2009 $0 $0 REMOVED
GLENVIEW DROP CEILING MAIN OFFICE        - GLENVIEW BUDGET 2009 $0 $0 REMOVED
$97,850 $76,391
 
DISTRICT PARKING LOT SEALING/REPAIR 2009 $15,000   COMPLETE
TOTAL DISTRICT 2009 $308,352  
 

YEAR

ESTIMATE

ACTUAL

 

STATUS

HIGH SCHOOL WINDOWS 18 ROOMS - SMALL WINDOWS 204-214 101-107 FROM 2009 2010 $25,000 $24,400 COMPLETE
HIGH SCHOOL  CAGING AUDITORIUM 2010 $5,000 $0 TBA
HIGH SCHOOL CONTROLS TO BOILERS, PUMPS 2010 $20,000 $40,000 COMPLETE
HIGH SCHOOL TILE - ROOMS 102  103 2010 $4,000 $4,545 COMPLETE
HIGH SCHOOL FIRE ALARM COMPLETED ALL 3 PHASES IN 2009-10 2010 $110,000 $130,000 COMPLETE
HIGH SCHOOL FIRE ALARM ENGINNERING FEES (new) 2010 $22,000 $17,600 COMPLETE
HIGH SCHOOL SIDEWALK REPLACEMENT SCHOOL TO STADIUM  (new) 2010 $15,000 $7,150 COMPLETE
HIGH SCHOOL BLEACHER REPAIRS - BOARDS 2010 $12,000 $7,600 COMPLETE
HIGH SCHOOL RETUCK WINDOWS MANY AREAS HIGH SCHOOL 2010 $3,000 $0 IN_PROGRESS
HIGH SCHOOL AUXILARY GYM WINDOW AREA FABRICATION OF WALL 2010 $6,000 $0 TBA
$222,000 $231,295
MIDDLE SCHOOL SIDEWALK REPLACEMENT FROM 2009 2010 $6,000 $5,800
MIDDLE SCHOOL SHED for storage - not approved by planning commission 2010 $0 $0
MIDDLE SCHOOL STORAGE LOCKERS & CABINETS 2010 $12,000 $11,400
    2010 $18,000 $17,200
 
WESTERLY CLASSROOM DROP CEILINGS (8) Classrooms 2010 $24,000 $20,750 COMPLETE
WESTERLY CLASSROOM LIGHTING REPLACEMENT (8) Classrooms 2010 $8,000 $5,500 COMPLETE
WESTERLY CLASSROOM DRINKING FOUNTAIN/SINK UPGRADE/REPAIR 2010 $6,000 $0 DELAYED
WESTERLY INSTALL CONTROL UNITS / BOILERS 2010 $15,000 $17,500 COMPLETE
WESTERLY TILED ROOM 2 2010 $4,000 $1,585 COMPLETE
WESTERLY ROOF TRAILER, TRAILER -REPAIRS PERFORMED BY BAY MTC 2010 $3,000 $300 COMPLETE
WESTERLY SECURITY CAMERA ADD CAMERAS -NEW DVR & MONITOR NEEDED 2010 $2,000 $6,565 COMPLETE
$62,000 $52,200
     
             
NORMANDY CARPET 2010 $4,000 $0   DELAYED
NORMANDY CONTROLS HEATING SYSTEM 2010 $15,000 $17,500   COMPLETE
NORMANDY RAILINGS - HANDICAP RAMP STEPS - TO BE PAID STIMULUS FUNDS 2010 $10,000 $0   DELAYED
NORMANDY SECURITY CAMERA CAMERAS PLAYGROUNDS, FRONT OF BUILDING 2010 $5,000 $7,000    
$34,000 $24,500    
     
GLENVIEW WINDOWS ROOM 107,108 2010 $15,000 $0   DELAYED
HANDICAP RESTROOM INSTALL - TO BE PAID STIMULUS FUNDS 2010 $10,000 $0 IN-PROGRESS
RAILINGS - HANDICAP RAMP NEW STEPS TO BE PAID STIMULUS FUNDS 2010 $5,000 $0 IN-PROGRESS
$30,000 $0
DISTRICT PARKING LOT REPAIRS, SEALING (MS), HS CEMENT DRIVE REPAIR 2010 $30,000 $24,500 COMPLETE
SEALING OF DISTRICT LOTS DONE BY BAY MTC - MATERIALS ONLY 2010 $25,000 $5,000 COMPLETE
$29,500
TOTAL - ALL SCHOOLS 2010 $357,000 $348,895 BUDGET MIN    
CONTINGENCY 10%  2010   $34,889  10% CONT  
DISTRICT TOTAL 2010   $383,784 BUDGET MAX 

 

 

 

 

 

 

 

YEAR

ESTIMATE

ACTUAL

 

STATUS

HIGH SCHOOL WINDOWS LIBRARY , GUIDANCE 2011 $25,000 $0 DELAY TO 2012
HIGH SCHOOL CAFÉ ROOF 130 + 131 13,500 SQ FT ROOF I-1,I-2  2011 $81,000 $81,000 $6.00 SQ FT
HIGH SCHOOL CAFÉ REMOVE CARPET INSTALL FLOORING 2001 $25,000 $0 DELAY TO 2012
HIGH SCHOOL OFFICE CARPET 2011 $9,000 $9,000
HIGH SCHOOL STADIUM TRACK RESURFACE 2011 $110,000 $0 DELAY TO 2013
HIGH SCHOOL LOCKER REPLACMENT PHASE 2 2011 $20,000 $0 DELAY TO 2016 
HIGH SCHOOL AUDITORIUM HEAT - UNITS FAILING 2011 $60,000 $60,000
HIGH SCHOOL LIGHT REPLACE - AUXILARY GYM 2011 $2,000 $0 DELAY -BOND
HIGH SCHOOL GYM FLOOR REPLACE 2011 $195,000 $195,000
$527,000 $345,000
MIDDLE SCHOOL REPAIRS/UPGRADES/ROOF 2011 $15,000 $15,000
$15,000 $15,000
WESTERLY GYM LIGHT REPLACE 2011 $2,500 $0 DELAY - BOND
WESTERLY RE-SEAL REPAIR PLAYGROUND 2011 $15,000 $0 DELAY TO 2015
WESTERLY FIRE ALARM REPLACE 2011 $72,000 $0 DELAY 2012
$89,500 $0
     
NORMANDY LIBRARY ROOF I,J,K 4300 SQ FT 2011 $25,800 $25,800    
NORMANDY CARPET 2011 $4,000 $0   DELAY
NORMANDY SEAM REPAIR - CRICKET DRAIN REPAIR 2011 $10,000 $10,000    
NORMANDY GYM LIGHT REPLACE 2011 $2,000 $0   DELAY - BOND
$41,800 $35,800    
   
GLENVIEW REPAIRS/UPGRADES 2011 $6,000 $6,000  
MAINTENANCE ROOF ON BUILDING NEEDS SEALED/REPAIRED 2011 $15,000 $15,000 ALT IF ROOFS COME IN LOW
DISTRICT PAVING REPAIRS & SEALING BY BAY MTC 2011 $20,000 $20,000
TOTAL - ALL SCHOOLS 2011 $684,300 $436,800 BUDGET MIN   
CONTINGENCY 10%  2011   $43,680 10% CONT  
DISTRICT TOTAL 2011   $480,480 BUDGET MAX 

 

YEAR

ESTIMATE

ACTUAL

 

STATUS

HIGH SCHOOL WINDOWS Library, Guidance 2012 $25,000 $25,000
HIGH SCHOOL INDUSTRIAL ARTS ROOF 7,500 SQ FT ROOF J,K          7.75 SQ FT 2012 $58,125 $58,125
HIGH SCHOOL LOCKER ROOM ADD WEST ROOF D 10,000 SQ FT      7.75 SQ FT 2012 $77,500 $77,500
HIGH SCHOOL CARPET, Café Floor Tile 2012 $26,000 $0 ALT FUNDING
HIGH SCHOOL PAVING 25% OF MAIN LOT PHASE 2 OF 4 2012 $80,000 $0 DELAY TO 2014
      $266,625 $160,625  
   
MIDDLE SCHOOL REPAIRS/UPGRADES 2012 $10,000 $10,000
WESTERLY CARPET 2012 $4,000 $4,000
WESTERLY PARKING LOT RE-PAVE 2012 $80,000 $0 ALT FUNDING
WESTERLY FIRE ALARM REPLACE  2012 $72,000 $0 ALT FUNDING
$156,000 $4,000
NORMANDY  ALL-PURPOSE ROOM ROOF N 5,185 SQ FT 2012 $36,295 $36,295
NORMANDY  MAIN ENTRANCE/HALL ROOF D  6,000 SQ FT 2012 $36,000 $36,000
NORMANDY  CARPET 2012 $4,000 $4,000
      $76,295 $76,295
GLENVIEW WINDOWS 107/108 2012 $15,000 $15,000
GLENVIEW FIRE ALARM  2012 $42,000 $0 DELAY TO 2014  ALT FUNDING
$57,000 $15,000
DISTRICT PAVING & SIDEWALK REPAIRS  2012 $15,000 $15,000
TOTAL - ALL SCHOOLS 2012 $580,920 $280,920 BUDGET MIN    
CONTINGENCY 10%  2012   $28,092 CONT  
DISTRICT TOTAL 2012   $309,012 BUDGET MAX

YEAR

ESTIMATE

ACTUAL

 

STATUS

HIGH SCHOOL AUDITORIUM WING AHU CONVERT ELECTRIC TO HOT WATER 2013 $25,000 $0 ALT FUNDING
HIGH SCHOOL WINDOWS - SCIENCE, ART 2013 $25,000 $25,000
HIGH SCHOOL SOUTH CLASSROOM ROOF P 23,500 SQ FT 2013 $188,000 $188,000
HIGH SCHOOL AUDITORIUM CARPET 2013 $25,000 $0 ALT FUNDING
HIGH SCHOOL AUDITORIUM SEAT RE-UPHOLSTER 2013 $35,000 $0 ALT FUNDING
HIGH SCHOOL HOME EC ROOM UPGRADE 2013 $60,000 $0 ALT FUNDING
HIGH SCHOOL STADIUM TRACK RESURFACE 2013 $125,000 $0 ALT FUNDING
$483,000 $213,000
 
MIDDLE SCHOOL REPAIRS/UPGRADES 2013 $10,000 $10,000
WESTERLY REPAIRS/UPGRADES 2013 $10,000 $10,000
     
NORMANDY GYM ROOF A,B 4,600 SQ FT 2013 $32,200 $32,200
 
GLENVIEW REPAIRS/UPGRADES 2013 $6,000 $6,000
       
K.T. ALLEN BOILER REPLACEMENT - ENERGY EFFICIENCY - END OF LIFE 2013 $20,000 $0 ALT FUNDING
DISTRICT PAVING & SIDEWALK REPAIRS  2013 $15,000 $15,000
DISTRICT CARPET / TILE REPLACEMENT 2013 $15,000 $15,000
TOTAL - ALL SCHOOLS 2013 $588,200 $301,200 BUDGET MIN    
CONTINGENCY 10%  2013   $30,120 CONT  
DISTRICT TOTAL 2013   $331,320 BUDGET MAX

YEAR

ESTIMATE

ACTUAL

 

STATUS

HIGH SCHOOL BOILER ROOM / OFFICE 7600 SQ FT 2014 $60,800 $60,800  
HIGH SCHOOL LOCKER PHASE 3 2014 $25,000 $0 DELAY TO 2020
HIGH SCHOOL FLOORING BAND ROOM 2014 $12,000 $12,000  
HIGH SCHOOL CHOIR BAND ROOF 8700 SQ FT ROOF C-1,C-2,C-3 2014 $60,900 $60,900  
HIGH SCHOOL AUDITORIUM ROOF B, B-2 14,000 SQ FT 2014 $98,000 $98,000  
HIGH SCHOOL MAIN LOT REPAVE 2014 $100,000 $100,000
$356,700 $331,700
       
GLENVIEW FIRE ALARM 2014 $50,000 $50,000
NORMANDY
WESTERLY
MIDDLE SCHOOL
DISTRICT PHONE SYSTEM IMPROVEMENTS - VOICE MAIL - SYSTEM UPGRADE 2014 $20,000 $20,000
DISTRICT PAVING & SIDEWALK REPAIRS  2014 $15,000 $15,000
DISTRICT CARPET/TILE REPLACEMENT 2014 $15,000
TOTAL - ALL SCHOOLS 2014 $456,700 $431,700 BUDGET MIN    
CONTINGENCY 10%  2014   $43,170 CONT  
DISTRICT TOTAL 2014   $474,870 BUDGET MAX

YEAR

ESTIMATE

ACTUAL

 

STATUS

HIGH SCHOOL GYM ADDITION WEST ROOF 15,700 SQ FT ROOF A 2015 $125,600 $125,600
HIGH SCHOOL WINDOWS - REMAINING OLD SINGLE PANE 2015 $25,000 $25,000
HIGH SCHOOL HVAC and or IMPROVED VENTILATION SCIENCE ROOMS 2015 $400,000 $0 ALT FUNDING  
$550,600 $0
NORMANDY PARKING LOT REPAVE 2015 $60,000 $60,000    
GLENVIEW  PAVING 2015 $30,000 $30,000
WESTERLY  PLAYGROUND AREA - RE-PAVE/REPAIR 2015 $15,000 $15,000    
  $0
DISTRICT PAVING & SIDEWALK REPAIRS  2015 $15,000 $15,000
DISTRICT CARPET/TILE REPLACEMENT 2015 $15,000 $15,000
TOTAL - ALL SCHOOLS 2015 $685,600 $285,600 BUDGET MIN  
CONTINGENCY 10%  2015 $68,560 CONT  
DISTRICT TOTAL 2015 $754,160 BUDGET MAX
 
 

YEAR

ESTIMATE

ACTUAL

 

STATUS

 
PLEASE NOTE: YEARS 2016-2020
XXX SPECIFIC DISTRICT CAPITAL NEEDS MORE THAN 5 YEARS OUT ARE XXX XXX XXX XXX
XXX DIFFICULT TO ACCATELY PROJECT DUE TO THE MECHANICAL NATURE XXX XXX XXX XXX
HIGH SCHOOL PAVING AUDITORIUM / ALLEY 2016 $40,000      
HIGH SCHOOL LOCKER REPLACEMENT PHASE 2 2016 $25,000    
WESTERLY ROOF REPLACEMENT ROOF C 8,200 SQ FT 2016 $65,600    
WESTERLY ROOF REPLACEMENT ROOF A 27,800SQ FT 2016 $222,400      
      $353,000    
       
GLENVIEW PARKING LOT TOPCOAT - REMOVE BACK PARKING AREA 2016 $40,000
DISTRICT PAVING & SIDEWALK REPAIRS  2016 $15,000
DISTRICT CARPET/TILE REPLACEMENT 2016 $15,000
TOTAL - ALL SCHOOLS 2016 $423,000 BUDGET MIN    
CONTINGENCY 10%  2016 $42,300 CONT  
DISTRICT TOTAL 2016 $465,300 BUDGET MAX
   

YEAR

ESTIMATE

ACTUAL

 

STATUS

HIGH SCHOOL EAST CLASSROOM ROOF 13,000 SQ FT 2017 $91,000 2017 TOTALS EXPENSE  
HIGH SCHOOL NEW HOME CONCESSION STAND 2017 $80,000 HIGH SCHOOL 271,000
HIGH SCHOOL CEMENT REPAIR / REPLACE 1/4 MILE DRIVE 2017 $100,000 K.T. ALLEN 30,000
$271,000 301,000
MIDDLE SCHOOL ADD RECESS PAVEMENT AREA 2017 $15,000
K.T. ALLEN PAVING - TOP COAT 2017 $30,000
DISTRICT PAVING & SIDEWALK REPAIRS  2017 $15,000
DISTRICT CARPET/TILE REPLACEMENT 2017 $15,000
TOTAL - ALL SCHOOLS 2017 $346,000 BUDGET MIN    
CONTINGENCY 10%  2017 $34,600 CONT  
DISTRICT TOTAL 2017 $380,600 BUDGET MAX
   
   

YEAR

ESTIMATE

ACTUAL

 

STATUS

HIGH SCHOOL HOME BLEACHER INSIDE 2000 SEAT $140 2018 $280,000   BOND
  $280,000
TOTAL - ALL SCHOOLS 2018   BUDGET MIN    
CONTINGENCY 10%  2018   BUDGET MAX 
DISTRICT TOTAL 2018  
 
HIGH SCHOOL HOME BLEACHER OUTSIDE  2020 $390,000
HIGH SCHOOL LOCKER REPLACEMENT PHASE 3 of 3 2020 $25,000
Plese note: additional capital needs for years 2017 & 2018 will be known
as the district needs change and mechanical systems wear. 
Other upcoming district needs
Metal Roof Replacement/Repair Normandy,Glenview,High School est 2019
Athletic fields dainage/improve depending on RR fundraising
Electrical upgrade high school
Boilers at Normandy and Westerly will require replace/major repair   
Boilers at HS are near end of life in year 2017 (25 years old)